Pottery Barn Kids


Selective Demolition

Owner: Delta Land Development

General Contractor- Phase 1: N. Wallace Construction

Phase 2: Fisher Developments

Scope of Work:
-
Reshoring of structure

-Removal and salvage of Main Floor Structure to enable excavation in the building

-Break and remove the concete canopy along Granville St.

Project Location: 2935 Granville St., Vancouver, BC

Completion Date: October 2008

The Challenge:

Complete removal of the main floor of the building. This would enable excavation to create a full basement. The entire roof structure was reinforced with bracing prior to dismantling work.





click the photo to enlarge